Our New Kitchen

The time has come to completely rework our kitchen. This will involve in this order, but that could change.


  1. Rip up floor tiles.
  2. Repair/replace the hole in the ceiling where the sky light was. 
  3. Remove the sliding door and frame.
  4. Remove all of the existing benches, sinks, cupboards, stove and cook top.
  5. Remove exhaust fan and replace that section of ceiling.
  6. Get contractor to put in new gas pipe for the new gas hob. 
  7. Get contractor to put in new power point for the microwave. 
  8. Repaint all walls and ceilings. 
  9. Install new cupboards and benches.
  10. Buy new stove, range-hood, dishwasher, microwave.
  11. Get the custom bench top measured and fitted.
  12. Install electrical appliances. 
  13. Rip up the tiles in the passage way, and pull up the carpets in the dining and family rooms.
  14. Lay new floor tiles in all of those rooms.
  15. Take care of anything else that pops up along the way.

Once that has been completed we will knock the bar down in the lounge room and convert the alcove  behind the bar into a cupboard to store the DVD player and the DVD's we have.

Please check back every now and then to check our progress.

Andrew

Tuesday, December 22, 2009

Finishing off the doorway.

The form work is in place ready for me to start applying the cement

Rhiannon tries her hand at rendering the wall.


The cement is in place.


After the cement dried I cut and added a piece of gyprock to each side of the door way.


This is the hall way side of the doorway.


Once the gryprock was in I started to fill in the gaps around the doorway.